Loading...
Hickman Road Over Tuolumne Bridge Project2021-11-29T11:08:20-07:00

Project Description

The Hickman Road over Tuolumne River Bridge Replacement Project will replace the existing bridge with a new 750-foot structure built immediately upstream. The existing bridge was built in 1964 and has been determined to be “Structurally Deficient”. The new bridge will provide two 12-foot traffic lanes with eight-foot shoulders and add a five-foot sidewalk for safe pedestrian and bicycle access.

The new Hickman Road Bridge will be a cast-in-place, post tension box girder consisting of five spans. It will be supported by two cast-in-drilled-hole pile shafts at each pier. The piles range from 84 to 108 inches in diameter, with lengths up to 123 feet. Approximately 450 feet of roadway will be realigned before and after the new bridge in order to conform into the existing Hickman Road.

Line Drawing Before / After Construction

Click To Expand

*Click Image To View Full Size View

Construction Schedule

Project Completion 85%

Project Schedule

Build New Bridge Begun June 2020
Complete New Bridge Late 2021
Demolition of Old Bridge Spring/Summer 2022
Estimate Project Completion Summer 2022

*Construction schedule is subject to change due to many factors including weather conditions.

Project Hotline: 209-399-2028

Key Project Elements

  • The first part of the bridge to be constructed is the foundation. This will include 8’ reinforced concrete pile shafts up to 10’ in diameter and 123’ deep. They will have to be constructed underwater using state-of-the-art construction techniques and testing processes to ensure the structural integrity of the bridge.

  • A temporary trestle is being constructed across the river to provide access for the bridge construction. This temporary structure will support cranes, pile driving equipment, concrete trucks, and other heavy construction equipment. It will remain in place for the duration of the bridge construction.
  • The new bridge will be up to 85’ above the ground. In order to build it, a tall “falsework” support structure must be constructed over the river. It will consist of 24” wide pipe piles, steel beams, and cable bracing. It is designed to support the entire weight of the new bridge until the bridge is completed.

  • The existing bridge is home to more than 6,000 bats. Mitigation measures will be taken to protect them during construction. The new bridge will include bat “houses” inside the box girder superstructure to provide a new home for the bat colony.

Project Location (Click to view in Google Maps)

FAQ

The Hickman Road Bridge was constructed in 1964 and has been determined by Caltrans to be “Structurally Deficient”. Specifically, the existing bridge is scour critical with acute undermining at the center three piers. Emergency repair efforts have reduced the rate of erosion, but the bridge supports continue to be undercut.

The project is financed with federal and local funds. Stanislaus County is the lead agency responsible for project delivery with support from the City of Waterford. Dewberry | Drake Haglan is the Project Designer and NV5 is the Construction Management Team. They will be working very closely with the project contractor, MCM Construction, to assure a successful and timely project.

The project will replace the existing 652.5-foot bridge with a new 750-foot structure built immediately to the east. The new bridge will provide two 12-foot traffic lanes with eight-foot shoulders and add a five-foot sidewalk for safe pedestrian and bicycle access. It will also carry a new waterline and other utilities.

The project is anticipated to be completed by the winter of 2021/2022. The estimated schedule is as follows:

Build new bridge: Begun June 2020

Complete new bridge: Mid 2021

Demolition of old bridge: Summer/Fall 2021

Estimate project completion: Winter 2021/2022

*Construction schedule is subject to change due to many factors including weather conditions.

Hickman Road will remain open throughout the majority of construction. However, there will be a two-week bridge closure during construction in order to connect the new bridge to the existing roadway. More information will be available as this date approaches.

The project will not prevent access to the river. However, for public safety, there will be times where the river will be closed through the construction site due to specific construction activities. Signs will be installed to notify the public of these closures.

Please visit the Photo Gallery for renderings of the new bridge.

Communication with the local and traveling public is a priority for Stanislaus County. For more information or to sign up for construction alerts, please visit www.hickmanbridge.com  For updates, questions or concerns, please contact the project hotline at (209) 399-2028 or email hickmanbridge@hickmanbridge.com

The project is being carefully constructed under a variety of environmental State and federal permits aimed at protecting fish, wildlife, plants, and water quality. A team of biologists, including fish, bat, bird, and water quality specialists are monitoring the project to help maintain compliance with all environmental requirements for a clean and safe project.

Highway Bridge Program (HBP), Local Seismic Safety Retrofit Program (LSSRP), and local fees.

Project Updates

Two-Week Road Closure

Two-Week Road Closure Details

Closure begins Monday morning, November 8 at 1:00 a.m. and ends Monday, November 22 at 2:00 p.m.

Please use the following detour routes:

City of Waterford to City of Hickman
Westbound on Yosemite Blvd/SR132
Southbound on Geer Road
Eastbound on E. Whitmore Avenue

City of Hickman to City of Waterford
Southbound on Hickman Road
Westbound on E. Whitmore Avenue
Northbound Geer Road
Eastbound on Yosemite Blvd/SR132

We appreciate your patience as we complete final construction of the new Hickman Road Bridge over Tuolumne River.

Project updates, road closures, construction alerts, and a 24-hour hotline are available on the project website: www.hickmanbridge.com.

By |October 18th, 2021|Categories: Construction Alerts|Comments Off on Two-Week Road Closure

Current Construction Update

Construction crews began work on Hickman Road over Tuolumne River Bridge Project on June 2020. The $18 million, 750-foot long, 75-foot tall, 5 span bridge replacement project has primarily involved building the bridge foundations and substructure. The bridge is supported on 100-foot deep piles with diameters ranging between 8 and 10 feet. All of the bridge abutments and columns have been completed.

Falsework and superstructure construction is currently underway, which consists of a 48-foot wide by 7-foot deep 3-cell, post-tensioned concrete box girder. Construction on the new bridge will continue into the winter.

Environmental Status
The project is being carefully constructed under a variety of environmental State and federal permits aimed at protecting fish, wildlife, plants, and water quality. A team of biologists, including fish, bat, bird, and water quality specialists are monitoring the project to help maintain compliance with all environmental requirements for a clean and safe project.

Project Funding
Funding for this project includes the Highway Bridge Program (HBP), Local Seismic Safety Retrofit Program (LSSRP), and local fees.

Email us or call the project hotline with any questions or concern and a project team member will get back to you – 209.399-2028.

Click thumbnail images to see enlarge images.

By |July 28th, 2021|Categories: Construction Alerts|Comments Off on Current Construction Update

Construction of the new bridge began in June.

Current work includes constructing a temporary trestle across the Tuolumne River. This will provide access for the equipment used to construct the bridge. Work has also begun on the bridge foundation. This includes constructing eight concrete piles ranging from 8’ to 10’ in diameter concrete pile extending nearly 120’ deep underground. After the piles are completed, the columns will be poured and layout of the new bridge will begin to take shape.

By |August 21st, 2020|Categories: Events|Comments Off on Construction of the new bridge began in June.

SIGN UP FOR PROJECT UPDATES

Keep Up-To-Date on Project Details

Fill in the form below to be added to our newsletter.

    Get In Touch

    Project Hotline: 209-399-2028

    Send Us A Quick Email

      Go to Top