Current work includes constructing a temporary trestle across the Tuolumne River. This will provide access for the equipment used to construct the bridge. Work has also begun on the bridge foundation. This includes constructing eight concrete piles ranging from 8’ to 10’ in diameter concrete pile extending nearly 120’ deep underground. After the piles are completed, the columns will be poured and layout of the new bridge will begin to take shape.